Knock Down Rebuild Melbourne 2026: The Real Timeline From Survey to Keys
Summary
The short version. A knock down rebuild in Melbourne takes 12 to 18 months from feature survey to occupancy permit when your block needs only a building permit, and 18 to 30 months when it triggers a planning permit. Construction is rarely the longest stage. The approvals, the demolition consent, and the service abolishments ahead of the excavator are where most owner-builders lose time. Your zone, your overlays, and your soil classification decide which pathway you are on, and you can find out the first two for free before you spend a dollar on design. Get those answers first, then plan the rest of the job around them.
Table of Contents
The slab on a Melbourne knock down rebuild is decided by ground you cannot properly see until the old house is gone. Large parts of the western and northern suburbs sit on basalt-derived clays that geotechnical engineers often classify H2 or E under AS 2870 (the Australian Standard for residential slabs and footings). The eastern and south-eastern suburbs are often kinder, more commonly M or H1. Remove a sixty-year-old house, its strip footings, and the tree that has been drawing moisture from under it for decades, and the site can be classified P, which means the engineer designs for abnormal moisture conditions rather than working from a standard table. That one letter can move you from a waffle pod to a stiffened raft or a pier system, and it moves your budget and your timeline with it.
The soil is one constraint. The planning controls on your title are the other, and between them they set the length of the job. If your block needs no planning permit, a realistic window from feature survey to occupancy permit is 12 to 18 months. If it sits in a Heritage Overlay, a Neighbourhood Character Overlay, or on a lot below your council’s single-dwelling threshold, plan for 18 to 30. Building the house is rarely the slowest part. Getting permission to knock the old one down often is.
What decides your pathway before anyone quotes it
Two documents tell you most of what you need to know, and between them they cost less than a tank of fuel. The first is a Planning Property Report from VicPlan, which is free and lists your zone and every overlay on the title. The second is a Regulation 51 property information request from council, which tells you about flood levels, termite areas, and previous permits for a small statutory fee.
The pathway follows from those results. In the General Residential and Neighbourhood Residential zones, a single dwelling on a lot under 300 square metres needs a planning permit and a Clause 54 (ResCode) assessment, and some councils raise that threshold to 500 square metres in their zone schedule. A Heritage Overlay means demolition itself needs a planning permit, and council can refuse it outright for a contributory building. A Special Building Overlay or Land Subject to Inundation Overlay brings Melbourne Water in as a referral authority. If none of that applies, you go straight to a building permit. We cover the difference between building and planning permits in more detail elsewhere, because the two get confused constantly and the confusion costs people months.
Twelve to thirty months, and why the range is that wide
That spread comes almost entirely from the stages before construction. The table below is the sequence we plan Melbourne rebuilds around, with the durations we see on typical single and double storey jobs. Some stages run in parallel, so the column does not add up neatly, and that is the point. The owner-builders who finish closest to 12 months are the ones who overlap the right stages.
| Stage | Typical duration | What owner-builders underestimate |
|---|---|---|
| Feature survey, soil test, property information | 3–6 weeks | Surveyor lead times, and limited bore locations around a standing house |
| Design and documentation | 8–14 weeks | How long their own decisions take |
| Planning permit (if triggered) | 3–9 months | Further information requests restart the 60-day statutory clock |
| Engineering, energy rating, building permit | 4–8 weeks | The council demolition consent inside the building permit |
| Owner-builder certificate of consent | 2–4 weeks | It must be issued before the building permit |
| Service abolishment (gas, power, water) | 4–10 weeks | Gas meter removal and electricity abolishment queues |
| Asbestos removal and demolition | 2–4 weeks | Five days notice to WorkSafe before licensed removal |
| Construction | 8–16 months | Gaps between trades when you are the one booking them |
| Final inspection and occupancy permit | 2–6 weeks | Outstanding certificates from plumbers and electricians |
Each stage, in the order it happens
Each of those rows has its own traps, and most of them are specific to how Victoria regulates demolition and owner-building.
Survey, soil, and site information
A feature and level survey should come before any design work, and it should pick up neighbouring windows, habitable rooms, and boundary fences, because the siting rules in Part 5 of the Building Regulations 2018 measure overlooking and overshadowing against them. Order the legal point of discharge from your water corporation at the same time. Yarra Valley Water, South East Water, and Greater Western Water all issue it, and its depth decides whether a lower floor can drain by gravity at all.
Design and documentation
This is the stage you control most and rush most. Eight to fourteen weeks covers concept, a round of changes, and construction drawings. Every change after the engineer has started costs both money and calendar time.
Planning permit, if your block triggers one
Victoria gives councils 60 statutory days, but a further information request stops the clock and it restarts from day one once you respond. Advertising adds at least two weeks, and objections can push the application to VCAT (the Victorian Civil and Administrative Tribunal), which adds months. In the middle-ring councils we deal with, four to eight months from lodgement is a fair expectation.
Building permit and the demolition consent
Your private building surveyor issues both the demolition permit and the building permit, but under section 29A of the Building Act 1993 they must first ask council whether it consents to the demolition. Council has 15 business days to respond. If the surveyor only lodges that request once your drawings are finished, you have just added three weeks for nothing.
Your certificate of consent
Owner-builders in Victoria need a certificate of consent from the Building and Plumbing Commission (which took over from the Victorian Building Authority in July 2025) for domestic building work valued over $16,000. That includes passing the owner-builder knowledge assessment. The building permit cannot be issued until the certificate is in hand, so apply early. Our guide to owner-builder permits covers eligibility and the obligations that come with it.
Disconnections, asbestos, and the demolition itself
Most Melbourne houses built before 1990 contain some asbestos, typically in eaves, wet-area linings, and older fibre cement cladding. Licensed removal needs at least five days notice to WorkSafe Victoria, and the demolisher, who must be registered with the Building and Plumbing Commission, should not start until a clearance certificate is issued. The demolition quotes we see for a standard single-storey brick veneer or weatherboard house in Melbourne land between $25,000 and $45,000, with asbestos adding $3,000 to $20,000 depending on how much there is and where it sits. Council will also want an asset protection permit and bond before machinery crosses the nature strip.
Construction and the occupancy permit
A single-storey owner-builder project in Melbourne typically runs 8 to 12 months on site, and a double storey 12 to 16. At the end, your surveyor needs compliance certificates from every licensed trade before issuing the occupancy permit. One missing plumbing certificate can hold the keys for weeks.
Owner-builder budget checklist. Demolition, asbestos, bonds, abolishment fees, and the soil-driven slab upgrade all land before the first stud goes up. Run your numbers through our owner-builder budget checklist so none of them arrive as a surprise.
Where Melbourne jobs lose their months
The delays we see on Melbourne rebuilds are rarely dramatic. They are small administrative waits that nobody scheduled, and they stack.
The first is service abolishment. Gas meter removal, electricity abolishment through distributors such as CitiPower, Jemena, United Energy, or AusNet, and sewer and water capping all run on their own queues, and the demolisher cannot start until all of them are done. Four weeks is a good outcome. Ten is not unusual. Related to this, if your rebuild needs a planning permit applied for after 1 January 2024, the new house cannot connect to the reticulated gas network, so the design has to be all-electric from the start rather than converted late.
The second is trees. Many councils, Boroondara and Whitehorse among them, have local laws protecting canopy trees above a set trunk size, and removing one without a permit is an offence. Finding a protected tree in the middle of your building envelope after the design is finished means redesigning around it or waiting on a permit decision.
The third is the planning further information request. Councils send them for things as small as a missing shadow diagram at a particular hour, and the statutory clock resets each time. A complete application on day one is the cheapest time-saver available to you.
The fourth is the owner-builder gap. When you run your own trades, the days between the frame inspection and the plumber’s rough-in are yours to manage. Two days lost per trade across fifteen trades is a month. Nobody sends you an invoice for it. You just move in later.
What Draftee does. We draw the plans, we don’t sell buildings. That means we have no stake in which builder, kit, or trade you use, and no reason to tell you the job is quicker or cheaper than it is. We prepare the concept, construction drawings, and permit documentation for owner-builders across Melbourne, and we coordinate with your surveyor and engineer so the paperwork moves while you get on with running the build.
Keeping your own build on schedule
The job does not get shorter by working faster on site. It gets shorter by overlapping the stages that do not depend on each other and refusing to start the ones that do before their inputs are ready.
In practice, that means ordering the feature survey, Regulation 51 information, and legal point of discharge in the same week. It means applying for your certificate of consent while the drawings are still being finished, and asking your building surveyor to request the section 29A demolition consent as soon as the demolition scope is known. It means lodging service abolishment the moment the building permit is lodged rather than issued, and booking the asbestos survey before you sign with a demolisher, so the quote reflects what is in the walls.
We have learned the cost of getting this order wrong. When we have let a design progress before the feature survey came back, we have ended up redrawing it once a neighbour’s habitable room window turned up three metres from the boundary. We do not do that anymore. The survey comes first, every time.
One more thing. Do not lock a construction start date with your slab contractor until the building permit is issued. She’ll be right is not a scheduling method.
The site decides the slab. The title decides the pathway. Everything else is sequencing.
Ready to draw? If you are planning a knock down rebuild in Melbourne and want plans prepared around your soil, your overlays, and your timeline, tell us about your block. We will come back to you with what your site needs and what the drawings involve. We work with owner-builders across NSW, VIC, QLD, WA, and TAS.
Continue Your Research

House Lifting Cost 2026: Raise, Build Under, and QLD Approvals

Cost to Build a Townhouse 2026: Real Numbers for Owner-Builders

Garage Conversion Melbourne 2026: Real Costs, Permits, and Timelines
This article is general information only and does not constitute legal, planning, engineering, or financial advice. Timelines and costs reflect projects we see across Melbourne and will vary with your site, your council, your soil classification, and market conditions. Planning controls, zone schedules, and local tree laws differ between Melbourne councils, so confirm your pathway with your council and a registered building surveyor before committing to a design or demolition. Victorian owner-builder requirements are administered by the Building and Plumbing Commission, which replaced the Victorian Building Authority from 1 July 2025, and requirements may change. The 7-star NatHERS minimum under NCC 2022 applies to new Victorian homes, and adoption dates and transitional provisions for NCC 2025 in Victoria should be confirmed with your building surveyor. If you sell an owner-built home within six and a half years of completion, you will need a defects report and domestic building insurance. Check current requirements before you build.
Last updated and changelog
Last updated: 12 October 2026
Changelog:
– 12 October 2026: Initial publication